Saturday, July 26, 2008
About the Center
   
About the Center
   
Calender
   
   

Quick Links
Power Sector in India - Challenges & Policy Options

Round Table Discussion on "Power Sector in India - Challenges & Policy Options" by Mr. Puneet K. Goel - Director, Ministry of Power, Government of India in Espire, A 41, MCIE, Mathura Road, New Delhi - 44.
26th JULY 08

HIGHLIGHTS
    Kilowatt, Mega watt and Per second energy produced

  • It is actually per second energy produced. What is per second energy produced? If you go to your physics, joule per second is the wattage. Suppose we consume one kilowatt of electricity for an hour, it is called kilowatt-hour. We get in our bills what we call units at home; it is actually kilowatt-hour, and the units are the same. In the power sector, when we say, we are often using two terms. If you read the Times of India or the Economic Times, sometimes they will mention peak shortage and sometimes energy shortage. These are two different problems. When they say peak shortage, it is actually megawatt shortage or kilowatt shortage. When energy shortage is mentioned, then it is actually kilowatt-hour shortage.


  • What Base load, peak load and Major Components

  • Talking about generation and distribution, there is another very important link between both. What is the difference between transmission and distribution? Transmission is at higher voltage. Why don't we transmit at lower voltage? Reverse current is v/r; when voltage is high, current will be low. Then why don't we use high voltage at our residences? We cannot, so there is a paradox. To reduce losses, we have to go for higher voltage, whereas for the safety of human beings we have to go for lower voltage. This question is very important because some of the developed countries have increased their voltages to very high level, to the extent possible outside their residences. Korea has the world's best power utility. And its size was half of India's total capacity. It has the world's minimum losses. They have achieved this by techno-managerial solutions. Through continuous research, they have gradually reduced their losses. Their losses are around 3.9%. Technically, it is a near-impossible feat. Compared to that, our losses are at 30%. Even the US has about 6% losses. But from our perspective, the good thing is that 30-40 years back, their losses were as high as India's. So there is some hope for India too.


  • Captive Generation

  • When you set up a plant for your own use and the definition is that you should use at least more than 50% of that power. And you should have equity of at least 26%. It need not be 50%, but the user should have equity of 26%, so that he has control over the company. Some people can set up a plant with 74% equity; this model is very much an upcoming one. In Tamil Nadu's industrial area, people are setting up plants with 74% equity and are asking the industrial consumers to hold 26% equity. They can then provide reliable supply. This was a new concept, which came up in the Electricity Act in 2000.


  • Open Access

  • Actually, either the power grid owns transmission lines or distribution lines are owned by distribution utilities. They sometimes may have excess capacity. What is grid? This is my last question. It is basically a high voltage network. We have five national grids.


  • Corporations

  • The Ministry of Coal has Coal India Limited with it and then it has Neyvelli Lignite Corporation. Then there is the Ministry of Power; many of the organisations are not statutory. One very important one is Central Electricity Regulatory Commission, which has come after the Electricity Act, 2003 and NTPC, PTC, Power Trading Company, Corporation for Power Finances. PTC is actually private; earlier, the majority of shares were held by government PSUs, now it is fully private. Then we have NHPC and the Ministry of Petroleum.
  • Korea has 21 nuclear plants. They have 21,000 megawatts capacity of nuclear energy running at almost full capacity; we have less than 3,000 and that too running at 30% plant load capacity.


  • Types of Plant

  • There are two types of plant in terms of their locations. One is a pithead plant and another is load centre plant. We have one in Badarpur and another in Dadri, which are basically load centres. They are more in the context of, this term is more in the context of coal-based plants or lignite based plants, in the context of hydro, everything has to be at the site only. And in terms of nuclear, it can be anywhere because carrying uranium is very risky. These three states, Jharkhand, Orissa and Chattisgarh, they are often arguing that government of India should not encourage too many plants in their states rather they should set up plants outside their states.


  • There are many plants in Jharkhand. Whenever a central company sets up a plant, there is a formula that it has to leave extra power to the hosts. So Orissa, Jharkhand and Chattisgarh get about 10% excess power apart from their normal power. They trade that additional power to other states, even U.P., which is very much lagging behind in setting up its own plants. And with that, they are subsidising their own consumers. Secondly, they also do not supply. Most of the unelectrified villages are in these districts.


  • Nuclear Programme

  • We have a three-stage nuclear programme. The first stage is based on uranium. We don't have uranium in plenty in our country, only sufficient for 3,000 megawatts. In the second stage, we will have fast breeder reactors. In the third stage, we will have plants from thorium, of which there is plenty in Kerala. We expect that by 2050, we should be able to produce about 2.5-lakh megawatts from this. In this context, nuclear energy is very important. The first and second stages of nuclear energy are very important.


  • Our hydro potential is 1,50, 000 megawatts. 33,000 megawatts lie in the Indus, 20,000 megawatts in the Ganges, then Brahmaputra, primarily in Arunachal Pradesh 66, 000 mega watts. But there are lot of difficulties in hydro. There are many environmentalists who delay projects for many years. Of course, there are problems of destruction of forests and rehabilitation. These plants have a certain life, for instance, Bhakra Nangal, but if we are able to construct some plants over - on the upstream of Bhakra Nangal - the life of any large multi-purpose hydro project will increase. Definitely, the environmentalists have a point to some extent. But at the same time, what we see is that much snow melts every year and goes into the sea. Thus every year, we lose a huge amount of electricity, which could have been used for the prosperity of the country. Again, hydro plants are very important to meet our peak load.


  • Ultra-Mega Power Projects

  • About two years back, the Government of India, i.e. the Ministry of Power had identified nine sites - nine projects - called ultra-mega power projects. There is no mystery in the term ultra-mega; it simply denotes size, which is 4,000 megawatts. Till now, we had plant size of 1000 mega watts. In this ultra mega also, there are two categories: one, is which are set up at a coast and another is which are at pithead locations. So we have one more category apart from pithead and load centre; the third category is coastal power plants. The idea was that if they have a power purchase agreement with the states, their return is guaranteed. Thus, private investors can come and tie up with Indonesia or South Africa and it will solve some of the problems. For one 4000-megawatt power plant, an investment of Rs16,000 crores is required. To get people to make this large investment, we in the ministry got all the clearances, acquired land for these power plants, gave them environmental clearance before bidding. We gave them limited blocks because these are the places where an investor has to do maximum running to get a coal block, to get an environmental clearance, water clearance, to get land. Therefore, the ministry of power, in coordination with the states identified these nine sites, and gradually, we have already awarded three projects. This is a very welcome change in the approach that has materialised in the last two years and I am sure the results will come in the next three years because the gestation period is about five years.


  • Types of Sites

  • There are pithead sites and coastal sites. Coastal are based on the imported coal. The developer has to tie up with coal on his own. We have so far awarded three projects; one is Sarsung where the Government of India has given the coal block. That's a pithead site. Then there are two more sites, one at Mundra and another at Krishnapatnam in Andhra Pradesh. These are coastal plants. Sarsung should be able to take care of the needs of the northern states and Mundra will take care of the needs of the western states and Krishnapatnam will take care of the needs of the southern states. And six more plants are in the pipeline. Sarsung is in Madhya Pradesh. We had created our own companies; those companies were given water clearance, land and environmental clearance and when the project was awarded, the entire company was transferred to the bidder, which is a new concept.


  • Some states like Orissa and Jharkhand, which are otherwise power surplus, do not supply to their own companies. They are selling at a very high cost to states like Delhi and Maharashtra. Earlier, the rates were very high and Power Trading Corporation was putting its own margin on that, regulator has kept that margin.


  • The Eleventh Plan says that our construction time is 40 months and development time is 24 months to set up a power plant. Similar to the manner they have developed these nine sites, India must develop at least 140 such sites - maybe on a small scale - if the supply has to exceed the demand by 2017.



PHOTOGALLERY
 


Former Indian Ambassador to USA



  


     

A-41, MCIE, Mathura Road
New Delhi - 110 044
Tel: 26991200 Fax: 26959999